Whenever a TBD Vendor is changed in BuildPro, the Load Calculator is
started, using the Task Start Date and the Task End Date as the time period.
If the Load Calculator returns an overload condition, you are notified
that the overload condition exists and you are asked if the vendor is
to be changed, or to go ahead and update despite the overload condition.
To assign suppliers
to plans/tasks:
Click the Plan
Task Name link. The Pending
TBD Suppliers page
opens.
Click the check box
in the Select column for each
task you want to assign to the new supplier.
Click the New
Supplier field and select a new supplier.
Click the Update
Tasks button.
To open the Job Task page
on the Jobs tab, click the Job Task
link.
|