Job Management

Fast Path: Complete Orders

Fast Path functions let you act on multiple tasks all on one page, with the click of a single button. Fast Path: Complete Orders provides a quick way to complete one or more orders at a time. Click here for a full explanation of the effects of changing the schedule.

 

To complete orders:

  1. Click the Subdivision field and select the appropriate subdivision.

  2. If needed, click the Supplier field and choose the appropriate supplier.

  3. Click the Job field and make the appropriate selection.

  4. If needed, change the Max Rows field.

  5. Click the Show Orders button. A list of orders appears. You can click the order number link to see the Order Detail page.

  6. Click the check box next to each order you want to complete.

  7. If the task is an MPO, the MPO pop-up window opens so you can enter the MPO Quantity. Click the Receive Qtys button. The pop-up window closes

  8. If the order is an NTE EPO, the NTE EPO pop-up window opens so you can enter the Actual Amount. Click the Update NTE Amount button. The pop-up window closes.

  9. If any order has open checklist items associated with it, they appear under the order number. To act on a checklist item, click the Passed or Failed option.

  10. Click the Complete Orders button at the bottom of the page.

 

If the Trade Partner Survey module is turned on for your company, questions will appear when completing some tasks. These questions must be answered before the task (PO) can be completed. Answer each question by clicking the Yes or No radio button. Enter notes as appropriate.

 

Related Topics