Fast Path: Complete Reminders

Fast Path functions let you act on multiple tasks all on one page, with the click of a single button. Fast Path: Complete Reminders provides a quick way to update reminders of things scheduled for completion. Click here for a full explanation of the effects of changing the schedule.

 

To complete reminders:

  1. Click the Subdivision field and select the appropriate subdivision.

  2. If needed, click the Supplier field and choose the appropriate supplier.

  3. Click the Job field and make the appropriate selection.

  4. If needed, change the Max Rows field.

  5. Click the Show Tasks button.

  6. Click the Check All button to mark all reminders as complete, or to mark individual reminders, click the check box next to the appropriate item.

  7. Click the Complete Reminders button.

 