The Add Task Direct page lets you to quickly add a task in a single
step.
Change the Task Name
field to reflect the name of the new task.
In the Description
field, type a brief description of the new task.
Click the Task Type
field and make the appropriate
selection.
Click the Account Code field
and make the appropriate selection for this task.
Click the Supplier
field and choose the appropriate supplier for this task.
Click the Supplier Industry field
and choose the industry that your supplier for this task is in.
In the Budget Amount field,
type the dollar amount budgeted for this task.
Check the Milestone Task box
if you are integrating your schedule with another system that uses milestones
and want this task to be considered as a milestone.
In the Milestone Key field,
type the task number to which this milestone task corresponds, if you
are integrating your schedule with another system that uses milestones.
Click the Stage
field and make the appropriate selection.
In the Lead Time
field, type the number of workdays required by a supplier or contractor
to schedule delivery for this task.
In the Duration
field, type the number of days required to complete the task.
Change the Sequence
field, if needed, to show the order you want this task shown on the schedule.
In the Offset
field, type the number of days to start a task earlier or later than it
normally would according to its rank.
Add any relevant instructions to the supplier in the
Supplier Instructions field.
Click the Add New Task
button. The Job Task page