Job Management

Job Schedule Management

The Job Schedule Management page shows each task within a specified stage. This page has two views: Graphical View and Advanced View. The Graphical View lets you change rank and duration for a task. The Advanced View lets you change rank, sequence, lead time, duration and offset for a task. A Job Admin can click the Add Pause Task link to pause any job for a short duration.

 

To use the Graphical View:

  1. In the box next to the appropriate task, change the Rank or Duration.

  2. Click the Reason field and make the appropriate selection for changing Rank or Duration.

  3. If needed, click the Schedule Change Supplier field and make the appropriate selection

  4. Type any relevant notes in the Explanation field.

  5. Click Update Job Schedule.

 

To use the Advanced View:

  1. In the box next to the appropriate task, change the Rank, Seq, Lead Time, Duration, or Offset.

  2. Click the Reason field and make the appropriate selection.

  3. If needed, click the Schedule Change Supplier field and make the appropriate selection

  4. Type any relevant notes in the Explanation field.

  5. Click Update Job Schedule.

 

Related Topics