The Job Schedule Management page provides job schedule information including
the stages of the job as well as the tasks within each stage. This information
can be displayed three different ways: Graphical (default), Advanced and
Stage. A Job Admin can click the Add
Pause Task link to pause any job for a short duration.
To change jobs:
Click the job name link, then select a new job name
from the Job Actions page.
To change predecessors
and sequencing of tasks (graphical view):
Next to the Task
name, change the value in the Predecessors
and Seq fields as needed.
Scroll down and click the
Schedule Change Reason field and
make the appropriate selection.
If needed, click the Schedule Change Supplier field and make
the appropriate selection
Type any relevant notes in
the Explanation field.
Click Update
Job Schedule.
To change predecessors,
sequence, lead time, duration and offset (advanced view):
Click the Advanced
View link.
Find the desired task, and
change the values in the columns as needed.
Scroll down and click the
Schedule Change Reason field and
make the appropriate selection.
If needed, click the Schedule Change Supplier field and make
the appropriate selection
Type any relevant notes in
the Explanation field.
Click Update
Job Schedule.
|