The Schedule Management: Task View shows each task in a template for
a specific stage, the task type (in parenthesis next to the task name),
each task’s rank, duration, and start/end dates, and a graphical view
of the length of each task. You have two views: Advanced and Stage. The
Advanced View lets you modify Rank, Sequence, Lead Time, Duration and
Offset for each task within a stage. The Stage View just shows the Start
and End Dates for each stage if the job using this template were to start
today.
The left navigation pane shows the Duration,
the number of Construction Days
and the End Date of a job that
would use this template (if the job started today). The Work Saturday
and Work Sunday indicators at the top of the page are used in this calculation.
To use Schedule Management-Task
View:
If needed, click the Stage
field and select a different stage.
To change the sequence, lead time or offset for a task,
click the Advanced View link.
Click a Task
link to view the Task Items page.
Change any Rank
and Duration and click Update
Template Schedule. The
End Date is changed for the stage.
|