The Late Active Tasks report shows, by subdivision, the job's primary
user and all tasks on a job that are behind schedule. The report also
shows the number of days behind schedule for each task and can be filtered
by date range. A task appears on the report if the task’s adjusted end
date is anytime before today’s date.
To generate the report:
Click the Subdivision
field to choose a Subdivision.
Click the User field
and choose the user name that you want to see for this report.
In the From and
To fields, type the date range
for the information you want to see.
Click Go.
Where does that come from?
Below is a list of information in the Late Active Tasks report and where
the information comes from.
Report
Filters
Subdivision
- Contains a list of all subdivisions with active jobs.
User -
Contains a list of active users that are the primary user on at least
one active job.
From: & To -
Allows the user
to further filter the report by inputting a date range. The date range
will filter tasks by the current start date.
Report
Columns
Job - Job
name. Same as the job name displayed on the Jobs home tab.
Task -
Shows the name of the task that is late. A task appears on the report
if the task’s adjusted end date is anytime before today’s date.
Start -
The adjusted start date of the task.
Expected
End - Shows the adjusted end date of the task.
Days Behind
- Shows the number of days this task is behind schedule. This is
difference
between the Expected End date and today’s date.
|