Reports

Late Active Tasks

The Late Active Tasks report shows, by subdivision, the job's primary user and all tasks on a job that are behind schedule. The report also shows the number of days behind schedule for each task and can be filtered by date range. A task appears on the report if the task’s adjusted end date is anytime before today’s date.

 

To generate the report:

  1. Click the Subdivision field to choose a Subdivision.

  2. Click the User field and choose the user name that you want to see for this report.

  3. In the From and To fields, type the date range for the information you want to see.

  4. Click Go.
     

Where does that come from?

Below is a list of information in the Late Active Tasks report and where the information comes from.

Report Filters

Subdivision - Contains a list of all subdivisions with active jobs.

User - Contains a list of active users that are the primary user on at least one active job.

From:  &  To -  Allows the user to further filter the report by inputting a date range. The date range will filter tasks by the current start date.  

Report Columns

Job - Job name. Same as the job name displayed on the Jobs home tab.

Task - Shows the name of the task that is late. A task appears on the report if the task’s adjusted end date is anytime before today’s date.

Start - The adjusted start date of the task.

Expected End - Shows the adjusted end date of the task.

Days Behind - Shows the number of days this task is behind schedule. This is difference between the Expected End date and today’s date.

 