The Completed Tasks by Week Summary report displays the number of tasks
that were completed each week during the year.
To generate the report:
Click the User drop-down
list and select the appropriate user.
Click the Supplier
drop-down list and select the supplier for the tasks on the report.
Click the Year drop-down
list and make the appropriate selection.
Click the Generate
Report button.
Where does that come from?
Below is a list of information in the Completed Tasks by Week Summary
Report and where the information comes from.
Report
Filters
User -
This is a list of all users. The default is 'All Users' but individual
users can be selected.
Supplier
- Can filter the report by a single supplier
or all suppliers. The default is 'All Suppliers.'
Date -
This filter will restrict the completed tasks shown by the date selected.
Report
Columns
Task/Job
- This is the task name and job name for the completed task.
Task Type
- The task type (PO, reminder, memo, etc).
Actual Start
- This is the date the task was started in BuildPro; not necessarily
the start date of the task.
Duration
- Number of days duration for the task.
Completed
Date - The date the task was marked complete in BuildPro.
Cost Code
- The cost code or accounting code assigned to the task.
Supplier
- The supplier assigned to the task.
Amount -
The dollar amount of the task or PO.
Tasks Found
- Total completed tasks for the week of the date chosen in the Date filter.
|