The Construction Schedule &endash; Phases report shows all phases for
a specific subdivision. Information includes the phase number, a numerical
listing of all jobs in this phase, the permit number for each job, lot
number, address for the job, the model (or template) used, elevation and
the swing of the garage.
To see the construction
schedule for a specific job:
Click the number link.
To see the construction
schedule for the phase:
Click the phase
number link.
Where
does that come from?
Below is a list of information in the Construction Schedule Report and
where the information comes from.
Report
Filters
Subdivision
- This is the name of the subdivision chosen from the previous
page.
Organization
- This is the name of the organization.
Report
Columns
Permit -
The permit number for the job from the job detail page.
Lot -
The legal lot number for the job.
Address
- Same as the job name displayed on the Jobs tab.
Model -
The BuildPro schedule template used to create the job.
Elev -
The Elevation designation for the job.
Garage -
The swing or side of the house the garage is on.
Primary
User - The primary user assigned to the job.
Phase Name
- The phase name is located in the blue bar, just above the listing
of permit numbers. This hyperlink shows the Construction Schedule Report
for all jobs in the phase.
|