The Job Close by Month - Job Summary report shows the initial (baseline)
start date and adjusted start date for all tasks within a specified job.
This gives you a quick view of the number of days behind or ahead of schedule
for each task.

|
If a task started early, the Days
Late column shows a negative number.
|
Where
does that come from?
Below is a list of information in the Job Close by Month Report and
where the information comes from.
Report
Filters
Job Name
- This is pulled from the Job Name field on the Job Detail Summary
page.
Subdivision
- This shows the subdivision name you chose from the previous page.
Phase -
This shows the name of the phase within the subdivision.
Report
Columns
Task Status
Icon - The icon next to the task indicates its status (Scheduled,
In Progress, Completed, Skipped, or Cancelled).
Task -
Shows all tasks for the job. Tasks in red have not been started, but should
have been started prior to the current date.
Supplier
- The Supplier column shows the name of
the company supplying the goods or services for this task.
Initial
Start - This is the baseline start date
for the task which is pulled from the Initial Date field on the Job Task
Schedule page.
Adjusted
Start - This is the adjusted start date for the task which is pulled
from the Adjusted Date field on the Job Task Schedule page.
Days Late
- Difference in days between the Initial
Start and Adjusted Start fields.
|