Job Initiation - Job Summary

The Job Initiation report shows a list of your organization's subdivisions and the number of phases in each. Click into a subdivision to more detail including baseline dates for job tasks, adjusted dates, and the number of days late for these tasks.

 

To generate the report:

  1. Click a subdivision link to open a list of all jobs that have started within the subdivision.

  2. Click a permit number to see task level detail for that job.

 

Where does that come from?

Below is a list of information in the Job Initiation Report and where the information comes from.

Report Filters

Job Name - This is the actual name of the job within the subdivision.

Subdivision - This field shows the name of the subdivision.

Phase - This field shows the phase name.

Selected - This field shows the address of the job you selected from the previous screen.

Report Columns

Task - The Task column shows all tasks for the job.

Supplier - Supplier associated to the task.

Initial Start - Baseline start date of the task.

Adjusted Start - The Adjusted Start column shows the date the task was started.

Days Late - Difference in days between the Initial Start and  Adjusted Start.

If a task started early, the Days Late column will show a negative number.

 

 