Job Status - Job Summary

The Job Status report shows you the status of jobs within a subdivision by stage and by task.

 

The Job Status report contains 3 sections:

  • Job Status - Active Subdivisions: shows a list of active subdivisions for your organizations, and the number of jobs within each subdivision.

  • Job Status - Active Subdivision Job: shows a list of active jobs within a specific subdivision and the status of each stage within the job.

  • Job Status - Job Summary:  shows the supplier, initial start date and adjusted start date for all tasks within a specified job. This gives you a quick view of the number of days behind schedule or ahead of schedule for each task.

 

To generate the report:

  1. Click the Generate Report button to view the Active Subdivision report.

  2. Click the appropriate Subdivision link to see a listing of jobs within that subdivision on the Active Subdivision Job report.

  3. Click the Job link to see task-level detail on the Job Summary report.

 

Where does that come from?

Below is a list of information in the Job Status report and where the information comes from.

Report Filters

Job Name - The name of the job that this report summarizes.

Subdivision - This shows the subdivision name you chose from the previous page.

Phase - This shows the name of the phase within the subdivision.

Report Columns

Task Status Icon - The icon next to the task indicates its status (Scheduled, In Progress, Completed, Skipped, or Cancelled).

Task - Shows all tasks for the job.  Tasks in red have not been started, but should have been started prior to the current date.

Supplier - The Supplier column shows the name of the company supplying the goods or services for this task.

Initial Start - This is the baseline start date for the task which is pulled from the Initial Date field on the Job Task Schedule page.

Adjusted Start - This is the adjusted start date for the task which is pulled from the Adjusted Date field on the Job Task Schedule page.

Days Late - Difference in days between the Initial Start and Adjusted Start columns.

If a task started early, the Days Late column will show a negative number.

 