Late Active Jobs - Job Summary

The Late Active Jobs report shows you a list of jobs that are behind schedule and the number of days they are behind. Click the Job name link to see the Late Active Jobs – Job Summary report, which shows a quick view of the number of days ahead or behind schedule for each task.

 

To generate the report:

  1. Select a subdivision or all subdivisions from the drop down box.

  2. Choose Yes or No from the Show Pause/Hold Days drop down box.

  3. Click Generate Report.

 

Where does that come from?

Below is a list of information in the Late Active Jobs report and where the information comes from.

Report Filters

Job Name - Name of the job selected from the previous page.

Subdivision - Name of the subdivision of the job.

Phase - Phase within the subdivision for the job.

Report Columns

Task - Shows the name of the task.

Supplier - Shows the name of the supplier for the task.

Initial Start - Shows the baseline start date for the task.

Adjusted Start - Shows the new, adjusted start date for the task, if the schedule has changed.

Days Late - Shows the difference between the Initial Start and the Adjusted Start.

Maximum Initial Start - The baseline start date farthest out in the job schedule- regardless of job stage.

Maximum Adjusted Start -The adjusted start date farthest out in the job schedule- regardless of job stage.

If a task started early, the Days Late column will show a negative number.

 