The Subdivision Job Status report shows, by user, the date the last
task was started and completed for a specific job.
To generate the report:
Click the Subdivision
field and choose the appropriate subdivision.
Click the User field
and choose the appropriate user.
Click the Generate
Report button.
Where
does that come from?
Below is a list of information in the Subdivision Job Status report
and where the information comes from.
Report
Filters
Subdivision
- Contains a list of all subdivisions with active jobs.
User - Allows
the user to filter the report by a specific job user.
Report
Columns
Task/Job
- This is the last task completed in the last complete stage. Job
name is the same as the job name displayed on the Jobs home tab.
Task Type
- The Task Type column shows the task type
designation (Memo, Purchase Order, Reminder, Contract, Measurement PO,
Work Order, etc).
Actual Start
- The Actual Start column shows the first date of the task or start
date.
Duration
- Number of days for the task in the BuildPro schedule.
Completed
Date - Date the user marked the task complete in BuildPro. Not
necessarily the end date of the task.
Task Category
- BuildPro Task Category for which the task belongs to. A task
does not have to be associated to a Task Category.
Completed
By - This shows the name of the user that completed the task.
Days Behind
- Difference in days between the baseline end date and the adjusted
end date of the task in the Task/Job column.
Jobs Found
- Total jobs listed that fit the filter criteria. (Shown on the last page
of the report.)
|