The Schedule Management: Task View shows each task in a template for
a specific stage, the task type (in parenthesis next to the task name),
each task’s rank, duration, and start/end dates, and a graphical view
of the length of each task. You have two views: Advanced and Stage. The
Advanced View lets you modify Rank, Sequence, Lead Time, Duration and
Offset for each task within a stage. The Stage View just shows the Start
and End Dates for each stage if the job using this template were to start
today.
The navigation pane shows the duration of a job using this template,
the number of construction days and the end date of a job using this template
(if the job started today). The red graph represents critical path items,
and the blue graph represents non-critical path items.
To use Schedule Management-Task View:
If needed, click the Stage
field and select a different stage.
To change the sequence, lead time or offset for
a task, click the Advanced View link.
Click a Task
link to view the Task Items page.
Change any Rank
and Duration and click Update
Template Schedule. The
End Date is changed for the stage.
|