The Schedule Management: Graphical View shows each task in a template
for a task predecessor job schedule, the task type (in parenthesis next
to the task name), each task’s stage, ID, predecessors, start/end dates,
sequence and a graphical view of the length of each task. You have three
views: Advanced, Stage and Task (or Graphical). The Advanced View lets
you modify the predecessors, sequence, lead time, duration and offset
for each task. The Stage View just shows the Start and End Dates for each
stage if the job using this template were to start today. The Task (or
Graphical) View is where you set your predecessor tasks and the sequence
of each task.
The navigation pane shows the duration of a job using this template,
the number of construction days and the end date of a job using this template
(if the job started today). The red graph represents critical path items,
and the blue graph represents non-critical path items.
|

|
The Task Type designation
is in parenthesis, next to each task name link. To see a legend of all
task types, scroll down to the bottom of your screen. |
To use Schedule Management:
If needed, click the Stage
field and select a different stage.
To change the sequence, lead time or offset for
a task, click the Advanced View link.
Click a Task
link to view the Task Items page.
From the Advanced
View, change any Rank and
Duration and click Update
Template Schedule. The
End Date is changed.
|