The Completed Tasks by Week Summary report displays the number of tasks
that were completed each week during the year.
Click the View
Printable link to generate
a printed copy of this report, or you can click the View
in Excel link to see the
data in MS Excel. Once the data is in Excel, you can arrange the data
to suit your needs.
To generate the report:
Click the User
drop-down menu and select the appropriate user.
Click the Supplier
drop-down menu and select the supplier for the tasks on the report.
Click the Year
drop-down menu and make the appropriate selection.
Click Accept
Filters.
Click the desired week on the calendar.
Where does that come from?
Below is a list of information in the Completed Tasks by Week Summary
Report and where the information comes from.
Report
Filters
User -
This is a list of all users. The default is 'All Users' but individual
users can be selected.
Supplier
- Can
filter the report by a single supplier or all suppliers. The default is
'All Suppliers'.
Year -
This filter will restrict the completed tasks shown by the year selected.
Monthly
Calendar - Click a specific week on the calendar and completed
tasks for that week appear on the report.
Report
Columns
Task/Job
- This is the task name and job name for the completed task.
Task Type
- The task type (PO, reminder, memo, etc).
Actual Start
- This is the date the task was started in BuildPro; not necessarily
the start date of the task.
Duration
- Number of days duration for the task.
Completed
Date - The date the task was marked complete in BuildPro.
Cost Code
- The cost code or accounting code assigned to the task.
Supplier
- The supplier assigned to the task.
Amount -
The dollar amount of the task or PO.
|