Construction Status

The Construction Status report shows, by subdivision, job status, and pause/hold days, the current status of each stage of a job. The report lets you see each job, the start date, the projected completion date and, how many days the job is ahead or behind schedule.

 

To generate the report:

  1. Select the Subdivision, Job Status, Show Pause/Hold Days, and Use Date Task Completed filters as needed.

  2. Click Generate Report.

 

The Milestone Module

You can view the milestone dates for each stage, on this report, if the milestone module is used For help on using milestones with this report contact Hyphen Solutions Support.  

If the milestone module is used, the report will display the maximum baseline end and maximum adjusted end dates for the stage’s milestone task. If there is more than one milestone task within the stage, the dates are used from the latest milestone task.

If the milestone module is turned not used, the report will display the maximum baseline end & maximum adjusted end for each stage.

Use the View Printable and View In Excel links for printing options.

 

Where Does That Come From?

Below is a list of information in the Construction Status Report and where the information comes from.

Report Filters

Org/Subdiv - Use the Subdivision drop down box to filter the report by that subdivision.

Job Status - Use the Job Status drop down box to filter the report by job status.

Show Pause/Hold Days - Use the Pause/Hold Days field to view the number of pause/hold days for a job.

Use Date Task Completed - The Use Date Task Completed filter will change the second date used in the stage column. 'Yes' will use the date the task was marked complete and 'No' will use the end date of the task.

Report Columns

Job Address - Same as the job name found on the jobs tab.

Start Date - Shows the start date of the job.

Various Stages - Show the stages for the jobs. The stage names can vary by job, subdivision, etc.

Job End Date - End date of the job.

Days +/- - Shows the number of days a job is ahead or behind schedule.

Pause Hold Days - Shows the total number of days for all Pause tasks in the job.

Net Days +/- - Shows the number of days a job is ahead or behind schedule.

The three dates within each Stage column represent:

  1. Top Date - Baseline end date for the stage.

  2. Middle Date - Adjusted end date for the stage.

  3. Bottom Date - Difference between the baseline and adjusted dates.

 

The three dates in the Job End Date column represent:

  1. The top date is the baseline end date for the job.

  2. The bottom date is the adjusted end date for the job.

  3. The number is the difference, in days, between the top date and the bottom date.

 