The Job Close by Month – Job Summary report shows the initial (baseline)
start date and adjusted start date for all tasks within a specified job.
This gives you a quick view of the number of days behind or ahead of schedule
for each task.
|

|
If a task started early, the Days
Late column will show a negative number.
|
Where does that come from?
Below is a list of information in the Job Close by Month Report and
where the information comes from.
Report
Filters
Job Name
- This is pulled from the Job Name field on the Job Detail Summary
page.
Subdivision
- This shows the subdivision name you chose from the previous page.
Phase -
This shows the name of the phase within the subdivision.
Report Columns
Task -
Shows all tasks for the job. Tasks in red have not been started, but should
have been started prior to the current date.
Supplier
- The
Supplier column shows the name of the company supplying the goods or services
for this task.
Initial
Start - This
is the baseline start date for the task which is pulled from the Initial
Date field on the Job Task Schedule page.
Adjusted
Start - This is the adjusted start date for the task which is pulled
from the Adjusted Date field on the Job Task Schedule page.
Days Late
- Difference
in days between the Initial Start and Adjusted Start fields.
|