BidConnect

Project Bid Analysis

The ultimate goal of BidConnect is to provide the builder the ability to compare bids from multiple vendors and determine which bid(s) will give them the best cost structure to meet their budget estimates for a bidding project. Additionally the user can export data to Excel in a format for uploading into the builder’s ERP system.

The bid analysis function is performed through a series of “views” based on Bid Groups. They are accessed by clicking on the Bid Analysis button on the Project Detail page on the Bid Analysis link in the left navigation bar. Each view (except the take-off item and option views) contains budget data as well as a column for each vendor who was invited to bid (and has submitted a bid response). They also include a row to “select” one vendor for the bid group that will be shown for that bid group on the Project Bid Summary page (see more detailed about “Selected Bidder” in the business rules section). For the discussions below, “base house” means bids that do not include options. It should also be noted that there is no budget data for options or take-off items. Each view also has a button for exporting the data for the given view in two formats; Export for ERP creates a spreadsheet which can be used to upload the awarded bids to the builder’s ERP system, Export to Excel provides the view data in Excel for them to do “off-line” analysis and manipulation in a format just like the view including drill down capabilities.

 

Bid Analysis Page Filters:

  1. Select the bid group from the Bid Group filter.

  2. Select the "view" (see description of views above) from the View filter.

  3. Click on the Select button.

    No data will be displayed on the Bid Analysis page until a bid group and view have been selected.

 

The views include:

 

Selected Bidder Row (row of check boxes below Bid Total row) (all views)

This row of check boxes provides a check box for each bidder who has been invited to bid on the cost codes for the bid group. Placing a check mark on one of the boxes “selects” that bidder and will cause that bidder’s bids to show up on the Project Bid Summary page for the bid group.

 

 

Bid Group Summary Rows (set of rows below the bid data rows)

The information in this section only applies to (both web page and Export to Excel spreadsheet):

  • Bid Analysis - Base House By Plans & Elevations

  • Bid Analysis - Base House by Cost Codes

 

 

Buttons/Actions