Use the Job Management Express page to quickly update start dates, adjust
task durations, mark tasks complete, skip tasks or submit PO’s for multiple
tasks at once. Multi-family jobs have their own version of JME. Click
here to view information about
the Multi-Family JME page.
There are four tabs available through Job Management Express: Schedule,
Reschedule, Detail and Re-Calc End Date. Each tab
is explained below and the functions available are on each. Click
here for a full explanation of the effects of changing the schedule.
Schedule tab:
This shows all tasks within a selected stage. From this tab you can start,
complete, change the duration, start date, or percent complete of a task.
Click one of the function names to
see detailed steps.
Change
the duration of a task
Complete
a task
Start
a task
Update
checklist items
Reschedule
tasks for a specific date
Mark
a task as rescheduled
Ignore
the reschedule notification for tasks
Detail tab: This tab shows each task name, rank, sequence,
lead time, duration, offset and skip. For predecessor schedules, the predecessor
ID is shown. Click one of the function names to see detailed steps.
Change
the duration of a task
Skip
a task
Re-Calc End Date: This
tab shows lets you do possible "what if" scenarios to facilitate
schedule acceleration. From this page, you can change the start date and
the duration of tasks that are Scheduled
or In Progress. If you
change theses fields and click Preview
Re-Calc, you see another page with the results of your schedule
changes. No changes are made to the actual schedule until you click the
Commit button. The column called
Lock This Date allows the user to hard code that task to the specific
date so that it will not move regardless of other changes in the schedule.
Click the function name below to see detailed steps for this tab.
Recalculate
the end date

|
Click the View
Printable link to have a copy of the Schedule tab that you can
send to your printer. |
To filter displayed job information:
Click the Job
Name field and select a different job.
Click the Stage
field and select a specific stage. The default is "All Stages.
Click the Status
field and select the appropriate status for the tasks you want to view.
Click the Task
Type field and choose the desired task type.
Click the Show
Tasks button.
To
update task information:
Click the Task link
and make the necessary updates or submit any orders from the Job
Task page.

|
If you click the link in
the Supplier Name column,
the Supplier Detail page
opens in a secondary window. |
If any
checklist item appears under a task, click the Passed
or Failed option as appropriate.
Click
the Update Job button
either at the top of the page, or at the bottom.
To change
a start date:
If a white box appears in
the Start Date column, you can
change the date if necessary, using MM/DD/YYYY as the
format.
If needed, click the Schedule Change Reason field and select
the appropriate reason for this schedule change.
If needed, click the Schedule Change Supplier field and make
the appropriate selection.
Add any relevant notes in
the Schedule Change Explanation
field.
Click the Update
Job button either at the top of the page, or at the bottom.
To change task duration:
From the appropriate
box in the Duration column, change
the number of workdays required to complete the associated task.
Click the Schedule
Change Reason field and choose the appropriate reason for making
this change.
In the
Schedule Change Explanation text box, type a brief explanation
for making this change.
Click the Update
Job button.
To start a task:
If needed, in the Start Date column, type the appropriate
start date for this task.
In the Start
column, click the associated box to start the task.

|
If there is an "X"
already in this column, it means the task has already begun. |
Click the Schedule Change Reason field and choose
the appropriate reason for making this change.
In the Schedule Change Explanation text box,
type a brief explanation for making this change.
Click the Update Job button either at the top
of the page, or at the bottom.
If the start
date is in the past, you will be asked if you want to allow task backdating.
Click OK if you do or Cancel
if you do not.
To complete a task:
In the Complete
column, check the appropriate box to mark a task complete, or type a percentage
of completion in the appropriate box for tasks that are in-progress.
NOTE:
A percent complete, even
100%, will
not complete a task
If
this is an MPO, a dialog box appears. In
the Rcv Now
field, type the quantity you received, even if it is less than the quantity
specified. Click Receive Qtys.
Towards the
lower left of the page, click the Schedule
Change Reason field and choose the reason for making this change.
In the Schedule
Change Explanation text box, type a brief explanation for making
this change.
Click the Update
Job button either at the top of the page, or at the bottom.
To skip a task:
Click the box in the
Skip column to skip a task.
Towards the lower left
of the page, click the Schedule Change
Reason field and choose the appropriate reason for making this
change.
In the Schedule
Change Explanation text box, type a brief explanation for making
this change.
Click the Update
Job button either at the top of the page, or at the bottom.
To
reschedule or ignore the reschedule notification:
Click the Reschedule
tab.
Find a task that has
a red flag next to it.

|
The red flag icon indicates
the task possibly needs to be rescheduled. |
Change
the Reschedule Date, if necessary.
To accept the
Reschedule Date, click the Reschedule
check box.

|
This also sends an order
reschedule notification to the supplier. |
To ignore the
reschedule notification, click the Ignore
check box.
Click
the Update Job button either at
the top of the page, or at the bottom.
To recalculate an end date:
Click the Job
Name field and select a different job.
Click the Stage
field and select a specific stage. The default is "All Stages.
Click the Status
field and select the appropriate status for the tasks you want to view.
Click the Task
Type field and choose the desired task type.
Click the Show
Tasks button.
Change the values in the Start Date or Duration
fields of the tasks where this information needs to be changed.
Click
the Preview Re-Calc button to
see the results of your changes.

|
Your Job Management Express
page refreshes with a Schedule NOT Updated
message at the top of the page. |
If needed, repeat steps 6
and 7 as many times as necessary until you see schedule changes that are
suited to your needs.
Click the box in the Lock This Date column next to any date
that needs to remain as shown on the schedule.
Click the Commit
button to update your schedule.
Other methods to reschedule a
task
You can also click the order number link and reschedule an order from
the Summary tab on the Order
Detail page.
|