Job Management

Phase Management - MPO / NTE EPO / Checklist Items

If a task has an MPO or Checklist Items, you can only complete that task after you have entered the MPO information and passed all of the Checklist Items. If you try to complete a task that has MPO or Checklist Items in Box Scheduling, the MPO/Checklist Items page will open.

 

To complete tasks with MPOs, NTE EPOs, or Checklist Items:

  1. Go to the Box Schedule or Task View page.

  2. Complete a task by entering the End Date and clicking the Update Tasks button.

  3. If the task is an MPO or NTE EPO or has checklist items, the MPO/Checklist Items page will open.

  4. Enter the Rcv Now quantity for MPO items.

  5. Enter Actual Amount for the NTE EPO.

  6. Click the Pass check box next to all checklist items.

  7. Click the Update button. This will take you back to your previous page (Box Schedule or Task View).

Or, click the Back button to return to the previous page without saving your changes. Those tasks will not be completed, but the date cells will remain green until you click on them again to un-highlight them.

  1. Click the Update button again to complete your tasks. If you don't click Update Tasks on the Box Schedule or Task View page ALSO, your changes will not be saved.

 