Job Management

Box Schedule/Task View - Sticky Date

Use Sticky Date to quickly change Start and End dates. Sticky Date also saves your original date until you update your changes, so it's easy to change it back.

To apply a Sticky Date in Box Schedule or Task View:

  1. Click in the Sticky Date field or on the calendar icon to pop up a calendar.

  2. Click on the calendar to select a date. Click on the arrows to move forward or backward to other months.

  3. Once you click on a date, your selected date will appear in the Sticky Date field.

  4. To remove the Sticky Date, click the Clear Sticky Date button.

  5. Click in the date fields of any Start and End Dates that you want to change to the Sticky Date. The changed fields will outline in green.

  6. Click back in the same field to change the date back to the original date.

  7. Click Update Tasks to save your changes. If you have View Possible Reschedules checked, the Reschedule Task page will now open.

The Sticky Date functionality is only available in Box Scheduling on the following pages: Box Schedule, Task View, and Reschedule Tasks.

 

Related Topics