Job Administration

Manage Centralized Scheduling Jobs

After Centralized Scheduling Groups have been created and Communities assigned to them, use this page to stagger Jobs within a Group by a specific Milestone Key. Stagger the Jobs by assigning a Start Sequence for each Job. Once the Jobs have been staggered, modify the Start Date of each Job to follow the Start Sequence.

Assign Start Sequence

  1. Select a Division.

  2. Select a Group.

  3. Enter the Milestone Key that you want to use in order to stagger the Start Dates.

  4. Click the Show Jobs button.

  5. Enter a Start Sequence for each Job. This is the order in which the will be built.

  6. Click the Update button.

Modify Start Dates

Repeat steps 1 through 4 above.

  1. Modify the Start Date of each Job so the dates are staggered and align with the order (Start Sequence) of which they will be built.

  2. Click the Update button.

 

After assigning a Start Sequence and modifying the Start Dates of Milestone Key tasks, Jobs may be managed from any BuildPro schedule management page. Box Scheduling (Task View), however, has a filter to allow the construction manager to filter by Centralized Scheduling Groups.

 

The Job List page will group Jobs by their Centralized Scheduling Group.