The Job Duration Analysis report displays the start date for the job,
the baseline end date, and adjusted end date, original duration of the
job and difference between the baseline and adjusted. Pause/hold days
can also be shown and factored in to this report. Use the View
Printable and View
In Excel links for printing options.
The Job Duration Analysis report is in three
sections:
Job Duration
Analysis – Select Subdivision Phase: shows a list of subdivisions
and the phases in each. Click a phase number link to select it and open
its Job Duration Analysis page.
Job
Duration Analysis - provides
an overview of the jobs within a specific subdivision phase.
Job
Duration Analysis – Schedule
Change Reason: details schedule changes made to a specific
job, by task.
To generate the report:
Click the appropriate Phase
link.
Set the filters for Job Status and Show Pause/Hold
Days
-
Click Generate Report.
Where does that come from?
Below is a list of information in the Job Duration Analysis Report and
where the information comes from.
Report Filters
Subdivision
- Subdivision selected from the previous page.
Phase -
Displays the name of the phase selected on the prior page.
Job Status
- Allows the user to filter the report by job status.
Show Pause/Hold
Days - By selecting Yes in the drop down box, two additional columns
are displayed on the report: Pause/Hold Days and Net Days. Selecting No
will hide these columns from the report.
Report Columns
Job - Job
name. Same as the job name displayed on the Jobs home tab. This link will
take the use to another page to view schedule changes and the schedule
change reasons.
Start Date
- Start date of the job from the job detail page. This may not
necessarily be the start date of the first task in the schedule.
Baseline
End/Duration - The maximum baseline end date of any task in the
schedule. Duration is calculated by the difference between the Start Date
and the Baseline End date.
Adj End/Duration
- The maximum adjusted end date of any task in the schedule. Duration
is calculated by the difference between the Start Date and the Adjusted
End.
Days Off:
The difference between the Duration of the Baseline column and the Duration
of the Adj column. .
Pause/Hold Days - Number of total days the job was placed on
hold or paused.
Net Days - Number
of Days Off plus Pause/Hold Days.
Status:
The Status
column shows the status of the job. (Active,
Complete, Canceled, etc)
|