\The Job Duration Analysis report displays the start date for the job,
the baseline end date, and adjusted end date, original duration of the
job and difference between the baseline and adjusted. Pause/hold days
can also be shown and factored in to this report. Use the View
Printable and View
In Excel links for printing options.
The Job Duration Analysis report is in three
sections:
Job Duration
Analysis – Select Subdivision Phase: shows a list of subdivisions
and the phases in each. Click a phase number link to select it and open
its Job Duration Analysis page.
Job
Duration Analysis - provides
an overview of the jobs within a specific subdivision phase.
Job
Duration Analysis – Schedule
Change Reason: details schedule changes made to a specific
job, by task.
To generate the report:
Click the appropriate Phase
link.
Set the filters for Job Status and Show Pause/Hold
Days
-
Click Generate Report.
Where does that come from?
Below is a list of information in the Job Duration Analysis Report and
where the information comes from.
Report Columns
Subdivision
- The
Subdivision column shows a list of your subdivisions.
Phase -
If
multiple phases exist for a subdivision, the user will see the subdivision
listed for every phase. The phase link will take the user to main report
page filtered by that subdivision/phase.
Active -
The status of the subdivision.
Job Count
- The
Job Count column shows the number of active jobs within the phase.
|