Template Management

Schedule Management: Stage View (Pred)

The Schedule Management: Stage View page displays each stage of the template, its Start and End dates, and a graphical view of the length of each stage. The Calculation Parameters section displays the Start Date (always based on today's date), Work Saturday and Work Sunday indicators (indicators are based on the user settings found on the Your Profile page). The Start and End dates are based on the earliest start date and latest end date of any task in that stage.

 

Three links appear at the top of this page:

  1. Graphical View - Use this page to update predecessors and sequence numbers.

  2. Advanced View - Similar to the Graphical View, but also allows the user to update lead times, durations, and offsets.

  3. Link Reminders and Memos to POs - This functionality is for integrated companies only. It allows the user to link reminders and memo tasks to a PO task. The linked reminders and memos will only be inserted into the job schedule if the PO task is added.

 

Click on a hyperlinked Stage name to view detailed information about each task in that stage.

 

Related Topics